TERMINAL ROAD ELEVATED STORAGE & PUMP STATION
City of Port Arthur, Texas
AWC provided surveying, design and construction project management services for the Terminal Road Elevated Tank & Pump Station project totalling approximately $7.6-million.
Project History
This project includes the construction of a new 2.5-MG elevated tank on a pile supported structural foundation, including two intermediate floors; four (4) booster pumps; electrical facilities & controls; and all of the internal piping for the automatic operation of the booster pump operation; a complete office with restroom facilities are located on the second floor for the City operating staff; a standby generator provided to power the booster pumps in all weather conditions, as needed; and, a hydropneumatic tanks to prevent surge on the distribution piping serving Pleasure Island.